<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <Name>Roadmap SIS · Transforma UAI</Name>
  <Title>Roadmap SIS · Transforma UAI</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Macroprocesos Académicos</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-02-24T08:00:00</Start>
      <Finish>2026-01-16T17:00:00</Finish>
      <Duration>PT2608H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>99</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Diseño · Configuración · Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-02-24T08:00:00</Start>
      <Finish>2026-01-16T17:00:00</Finish>
      <Duration>PT2608H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>99</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>01 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-02-24T08:00:00</Start>
      <Finish>2025-11-14T17:00:00</Finish>
      <Duration>PT2104H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>01 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-03T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT1960H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>01 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-26T08:00:00</Start>
      <Finish>2025-12-24T17:00:00</Finish>
      <Duration>PT1696H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>01 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-26T08:00:00</Start>
      <Finish>2025-12-31T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>02 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-03-24T08:00:00</Start>
      <Finish>2025-11-13T17:00:00</Finish>
      <Duration>PT1872H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>02 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-23T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT1800H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>02 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-06-03T08:00:00</Start>
      <Finish>2025-12-26T17:00:00</Finish>
      <Duration>PT1648H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>02 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-29T08:00:00</Start>
      <Finish>2026-01-02T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>03 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-07T08:00:00</Start>
      <Finish>2025-11-14T17:00:00</Finish>
      <Duration>PT1768H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>03 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-07T08:00:00</Start>
      <Finish>2025-11-19T17:00:00</Finish>
      <Duration>PT1568H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>03 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-06-18T08:00:00</Start>
      <Finish>2025-12-29T17:00:00</Finish>
      <Duration>PT1552H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>03 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-30T08:00:00</Start>
      <Finish>2026-01-05T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>04 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-21T08:00:00</Start>
      <Finish>2025-11-14T17:00:00</Finish>
      <Duration>PT1656H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>04 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-29T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT1512H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>04 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-07-14T08:00:00</Start>
      <Finish>2026-01-06T17:00:00</Finish>
      <Duration>PT1408H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>04 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-07T08:00:00</Start>
      <Finish>2026-01-08T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>05 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-12T08:00:00</Start>
      <Finish>2025-11-17T17:00:00</Finish>
      <Duration>PT1512H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>05 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-06-18T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT1352H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>05 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-08-19T08:00:00</Start>
      <Finish>2026-01-08T17:00:00</Finish>
      <Duration>PT1136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>05 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-09T08:00:00</Start>
      <Finish>2026-01-14T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>06 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-26T08:00:00</Start>
      <Finish>2025-11-17T17:00:00</Finish>
      <Duration>PT1400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>06 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-10-01T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT512H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>06 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-23T08:00:00</Start>
      <Finish>2026-01-12T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>76</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>06 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-13T08:00:00</Start>
      <Finish>2026-01-14T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>33</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>07 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-07-14T08:00:00</Start>
      <Finish>2025-11-18T17:00:00</Finish>
      <Duration>PT1016H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>07 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-10-01T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT512H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>07 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-24T08:00:00</Start>
      <Finish>2026-01-15T17:00:00</Finish>
      <Duration>PT176H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>07 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-16T08:00:00</Start>
      <Finish>2026-01-19T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>08 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-07-29T08:00:00</Start>
      <Finish>2025-12-05T17:00:00</Finish>
      <Duration>PT1032H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>08 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-10-01T08:00:00</Start>
      <Finish>2025-12-05T17:00:00</Finish>
      <Duration>PT520H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>08 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-12-29T08:00:00</Start>
      <Finish>2026-01-19T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>08 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-20T08:00:00</Start>
      <Finish>2026-01-21T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>09 · Diseño</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-07-14T08:00:00</Start>
      <Finish>2025-11-17T17:00:00</Finish>
      <Duration>PT1008H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>09 · Configuración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-10-13T08:00:00</Start>
      <Finish>2025-12-04T17:00:00</Finish>
      <Duration>PT416H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>09 · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-02T08:00:00</Start>
      <Finish>2026-01-21T17:00:00</Finish>
      <Duration>PT152H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>09 · Actualización EBP y LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-01-22T08:00:00</Start>
      <Finish>2026-01-23T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Macroprocesos Financieros</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-03-17T08:00:00</Start>
      <Finish>2026-12-22T17:00:00</Finish>
      <Duration>PT5160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>63</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Diseño LD · Pruebas Unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-03-17T08:00:00</Start>
      <Finish>2026-12-22T17:00:00</Finish>
      <Duration>PT5160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>63</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>10 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>10 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-03T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>10 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-31T08:00:00</Start>
      <Finish>2026-09-01T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>11 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>11 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2026-09-11T17:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>11 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-14T08:00:00</Start>
      <Finish>2026-09-17T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>12 · Construcción LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-18T08:00:00</Start>
      <Finish>2026-06-12T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>48</UID>
      <ID>48</ID>
      <Name>12 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>49</UID>
      <ID>49</ID>
      <Name>12 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-24T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>50</UID>
      <ID>50</ID>
      <Name>12 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2026-09-30T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>51</UID>
      <ID>51</ID>
      <Name>13 · Construcción LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-06-25T17:00:00</Finish>
      <Duration>PT192H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>52</UID>
      <ID>52</ID>
      <Name>13 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>53</UID>
      <ID>53</ID>
      <Name>13 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-14T08:00:00</Start>
      <Finish>2026-10-16T17:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>54</UID>
      <ID>54</ID>
      <Name>13 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-10-19T08:00:00</Start>
      <Finish>2026-10-20T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>55</UID>
      <ID>55</ID>
      <Name>14 · Construcción LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-24T08:00:00</Start>
      <Finish>2026-10-08T17:00:00</Finish>
      <Duration>PT112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>56</UID>
      <ID>56</ID>
      <Name>14 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-10-09T08:00:00</Start>
      <Finish>2026-10-16T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>57</UID>
      <ID>57</ID>
      <Name>14 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-10-12T08:00:00</Start>
      <Finish>2026-12-17T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>58</UID>
      <ID>58</ID>
      <Name>14 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-12-18T08:00:00</Start>
      <Finish>2026-12-22T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>59</UID>
      <ID>59</ID>
      <Name>15 · Construcción LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-08T08:00:00</Start>
      <Finish>2026-07-02T17:00:00</Finish>
      <Duration>PT192H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>60</UID>
      <ID>60</ID>
      <Name>15 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>61</UID>
      <ID>61</ID>
      <Name>15 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-28T08:00:00</Start>
      <Finish>2026-10-30T17:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>62</UID>
      <ID>62</ID>
      <Name>15 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-11-02T08:00:00</Start>
      <Finish>2026-11-03T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>63</UID>
      <ID>63</ID>
      <Name>16 · Construcción LD</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-15T08:00:00</Start>
      <Finish>2026-07-09T17:00:00</Finish>
      <Duration>PT192H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>64</UID>
      <ID>64</ID>
      <Name>16 · Carga LD y Validación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>65</UID>
      <ID>65</ID>
      <Name>16 · Prueba unitarias</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-10-26T08:00:00</Start>
      <Finish>2026-11-20T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>66</UID>
      <ID>66</ID>
      <Name>16 · Cierre fase de diseño, config y pruebas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-11-23T08:00:00</Start>
      <Finish>2026-11-24T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>67</UID>
      <ID>67</ID>
      <Name>Migración Datos Académicos</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-03-20T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT4968H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>61</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>68</UID>
      <ID>68</ID>
      <Name>Round 1-2 + Round 3 + Carga final</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-03-20T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT4968H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>61</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>69</UID>
      <ID>69</ID>
      <Name>Round 3 · Taskforce</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2026-05-04T17:00:00</Finish>
      <Duration>PT392H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>89</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>70</UID>
      <ID>70</ID>
      <Name>Script · Extracción estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-04T08:00:00</Start>
      <Finish>2026-05-15T17:00:00</Finish>
      <Duration>PT88H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>71</UID>
      <ID>71</ID>
      <Name>Script · Extracción historia académica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-04T08:00:00</Start>
      <Finish>2026-05-22T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>90</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>72</UID>
      <ID>72</ID>
      <Name>Script Transformación Persona/Docente/Convalid.</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-04T08:00:00</Start>
      <Finish>2026-05-20T17:00:00</Finish>
      <Duration>PT128H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>65</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>73</UID>
      <ID>73</ID>
      <Name>Validación funcional Persona/Docente/Convalid.</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-22T08:00:00</Start>
      <Finish>2026-05-29T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>74</UID>
      <ID>74</ID>
      <Name>Script Transformación Estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-18T08:00:00</Start>
      <Finish>2026-05-29T17:00:00</Finish>
      <Duration>PT88H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>75</UID>
      <ID>75</ID>
      <Name>Script Transformación Historia Académica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-18T08:00:00</Start>
      <Finish>2026-06-05T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>76</UID>
      <ID>76</ID>
      <Name>Actualización estrategia de migración</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-27T08:00:00</Start>
      <Finish>2026-07-29T17:00:00</Finish>
      <Duration>PT744H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>11</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>77</UID>
      <ID>77</ID>
      <Name>Análisis de calidad carga final</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-21T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT1792H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>4</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>78</UID>
      <ID>78</ID>
      <Name>Round 3 · Carga Persona General y Docentes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-04T08:00:00</Start>
      <Finish>2026-07-31T17:00:00</Finish>
      <Duration>PT456H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>79</UID>
      <ID>79</ID>
      <Name>Round 3 · Carga Estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-22T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT536H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>80</UID>
      <ID>80</ID>
      <Name>Round 3 · Carga Historia Académica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-30T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT472H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>81</UID>
      <ID>81</ID>
      <Name>Round 3 · Carga Convalidación</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-05T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT672H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>82</UID>
      <ID>82</ID>
      <Name>Nueva carga · Inscripción de asignaturas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-08-31T17:00:00</Finish>
      <Duration>PT728H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>83</UID>
      <ID>83</ID>
      <Name>Migración Datos Financieros</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-04-06T08:00:00</Start>
      <Finish>2027-04-16T17:00:00</Finish>
      <Duration>PT3000H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>10</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>84</UID>
      <ID>84</ID>
      <Name>Migración financiera</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-04-06T08:00:00</Start>
      <Finish>2027-04-16T17:00:00</Finish>
      <Duration>PT3000H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>10</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>85</UID>
      <ID>85</ID>
      <Name>Ellucian - Plataforma</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-03-06T08:00:00</Start>
      <Finish>2026-06-25T17:00:00</Finish>
      <Duration>PT3808H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>94</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>86</UID>
      <ID>86</ID>
      <Name>Ethos · Experience · EIP · ILP · Insights</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-03-06T08:00:00</Start>
      <Finish>2026-06-25T17:00:00</Finish>
      <Duration>PT3808H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>94</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>87</UID>
      <ID>87</ID>
      <Name>Ethos Implementation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-09T08:00:00</Start>
      <Finish>2025-11-27T17:00:00</Finish>
      <Duration>PT1856H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>88</UID>
      <ID>88</ID>
      <Name>Experience Implementation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-03-20T08:00:00</Start>
      <Finish>2025-07-11T17:00:00</Finish>
      <Duration>PT904H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>89</UID>
      <ID>89</ID>
      <Name>Ethos User Provisioning (EUP)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-08T08:00:00</Start>
      <Finish>2025-10-29T17:00:00</Finish>
      <Duration>PT1392H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>90</UID>
      <ID>90</ID>
      <Name>Ethos Integration Architecture Design Workshop</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-21T08:00:00</Start>
      <Finish>2025-05-22T17:00:00</Finish>
      <Duration>PT248H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>91</UID>
      <ID>91</ID>
      <Name>Ellucian Intelligent Processing (EIP)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-23T08:00:00</Start>
      <Finish>2025-07-03T17:00:00</Finish>
      <Duration>PT328H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>92</UID>
      <ID>92</ID>
      <Name>Intelligent Learning Platform (ILP)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-03-06T08:00:00</Start>
      <Finish>2025-10-15T17:00:00</Finish>
      <Duration>PT1784H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>99</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>93</UID>
      <ID>93</ID>
      <Name>Insights</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-04-24T08:00:00</Start>
      <Finish>2025-09-10T17:00:00</Finish>
      <Duration>PT1112H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>94</UID>
      <ID>94</ID>
      <Name>ISE Job Scheduling</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-29T08:00:00</Start>
      <Finish>2026-06-25T17:00:00</Finish>
      <Duration>PT3136H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>22</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>95</UID>
      <ID>95</ID>
      <Name>Ellucian - Localizaciones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-03-31T08:00:00</Start>
      <Finish>2026-10-28T17:00:00</Finish>
      <Duration>PT1688H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>25</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>96</UID>
      <ID>96</ID>
      <Name>Releases Mar→Sep 2026</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-03-31T08:00:00</Start>
      <Finish>2026-10-28T17:00:00</Finish>
      <Duration>PT1688H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>25</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>97</UID>
      <ID>97</ID>
      <Name>Release Marzo</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-31T08:00:00</Start>
      <Finish>2026-04-29T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>98</UID>
      <ID>98</ID>
      <Name>Release Abril</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-30T08:00:00</Start>
      <Finish>2026-05-29T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>57</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>99</UID>
      <ID>99</ID>
      <Name>Release Mayo</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-29T08:00:00</Start>
      <Finish>2026-06-26T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>100</UID>
      <ID>100</ID>
      <Name>Release Junio</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-30T08:00:00</Start>
      <Finish>2026-07-28T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>101</UID>
      <ID>101</ID>
      <Name>Release Septiembre</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-30T08:00:00</Start>
      <Finish>2026-10-28T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>102</UID>
      <ID>102</ID>
      <Name>Ellucian - APIs GAP</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>103</UID>
      <ID>103</ID>
      <Name>SGASTDN · SMARQCM · SVACTES · SFAREGS</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>104</UID>
      <ID>104</ID>
      <Name>API GAP SGASTDN</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>105</UID>
      <ID>105</ID>
      <Name>API GAP SMARQCM</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>106</UID>
      <ID>106</ID>
      <Name>API GAP SVACTES</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>107</UID>
      <ID>107</ID>
      <Name>API GAP SFAREGS</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-05-07T17:00:00</Finish>
      <Duration>PT528H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>100</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>108</UID>
      <ID>108</ID>
      <Name>Ellucian - Integraciones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-11-21T08:00:00</Start>
      <Finish>2026-05-25T17:00:00</Finish>
      <Duration>PT1480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>72</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>109</UID>
      <ID>109</ID>
      <Name>INT03 Admisión · INT02 ERP Financiero</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-11-21T08:00:00</Start>
      <Finish>2026-05-25T17:00:00</Finish>
      <Duration>PT1480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>72</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>110</UID>
      <ID>110</ID>
      <Name>INT03 · Admisión → Banner Student</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-11-21T08:00:00</Start>
      <Finish>2026-01-15T17:00:00</Finish>
      <Duration>PT440H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>92</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>111</UID>
      <ID>111</ID>
      <Name>INT02 · Banner Student → ERP Financ.</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-15T08:00:00</Start>
      <Finish>2026-05-25T17:00:00</Finish>
      <Duration>PT320H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>44</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>112</UID>
      <ID>112</ID>
      <Name>UAI - Experience</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-07-28T08:00:00</Start>
      <Finish>2026-10-09T17:00:00</Finish>
      <Duration>PT3504H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>38</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>113</UID>
      <ID>113</ID>
      <Name>Experience Cards (28)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-07-28T08:00:00</Start>
      <Finish>2026-10-09T17:00:00</Finish>
      <Duration>PT3504H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>38</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>114</UID>
      <ID>114</ID>
      <Name>Experience Card Académico Parte 1 (22)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-07-28T08:00:00</Start>
      <Finish>2026-06-19T17:00:00</Finish>
      <Duration>PT2608H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>58</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>115</UID>
      <ID>115</ID>
      <Name>Experience Card Académico Parte 2 (6)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-11T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT1120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>2</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>116</UID>
      <ID>116</ID>
      <Name>Tarjetas adicionales UX</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-10-09T17:00:00</Finish>
      <Duration>PT1040H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>117</UID>
      <ID>117</ID>
      <Name>UAI - Workflows</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-11-17T08:00:00</Start>
      <Finish>2027-08-30T17:00:00</Finish>
      <Duration>PT5208H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>30</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>118</UID>
      <ID>118</ID>
      <Name>WF EIP UAI (21)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-11-17T08:00:00</Start>
      <Finish>2027-08-30T17:00:00</Finish>
      <Duration>PT5208H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>30</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>119</UID>
      <ID>119</ID>
      <Name>WF Académico Parte 1 (13)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-11-17T08:00:00</Start>
      <Finish>2026-07-03T17:00:00</Finish>
      <Duration>PT1824H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>39</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>120</UID>
      <ID>120</ID>
      <Name>WF Académico Parte 2 (4)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-05-05T08:00:00</Start>
      <Finish>2026-09-08T17:00:00</Finish>
      <Duration>PT1008H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>2</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>121</UID>
      <ID>121</ID>
      <Name>WF Post Golive (4)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-05-14T17:00:00</Finish>
      <Duration>PT1040H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>122</UID>
      <ID>122</ID>
      <Name>UAI - Integraciones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-05-19T08:00:00</Start>
      <Finish>2027-05-27T17:00:00</Finish>
      <Duration>PT5904H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>38</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>123</UID>
      <ID>123</ID>
      <Name>Integraciones UAI (49)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-05-19T08:00:00</Start>
      <Finish>2027-05-27T17:00:00</Finish>
      <Duration>PT5904H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>38</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>124</UID>
      <ID>124</ID>
      <Name>Integraciones UAI Académico Parte 1 (24)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-05-19T08:00:00</Start>
      <Finish>2026-07-17T17:00:00</Finish>
      <Duration>PT3392H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>74</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>125</UID>
      <ID>125</ID>
      <Name>Integraciones UAI Académico Parte 2 (12)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-02T08:00:00</Start>
      <Finish>2026-10-05T17:00:00</Finish>
      <Duration>PT1736H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>6</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>126</UID>
      <ID>126</ID>
      <Name>Integraciones Post Golive (12)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-11-02T08:00:00</Start>
      <Finish>2027-05-27T17:00:00</Finish>
      <Duration>PT1648H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>127</UID>
      <ID>127</ID>
      <Name>UAI - Insights</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-08-28T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT3168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>80</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>128</UID>
      <ID>128</ID>
      <Name>Insights UAI (22)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-08-28T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT3168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>80</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>129</UID>
      <ID>129</ID>
      <Name>Reportes UAI Académico Parte 1 (21)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-10-13T08:00:00</Start>
      <Finish>2026-05-26T17:00:00</Finish>
      <Duration>PT1800H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>87</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>130</UID>
      <ID>130</ID>
      <Name>Reportes UAI Académico Parte 2 (2)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT952H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>131</UID>
      <ID>131</ID>
      <Name>UAI - DataConnect</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-09-22T08:00:00</Start>
      <Finish>2026-08-14T17:00:00</Finish>
      <Duration>PT2608H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>51</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>132</UID>
      <ID>132</ID>
      <Name>DataConnect Carga Masiva (13)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-09-22T08:00:00</Start>
      <Finish>2026-08-14T17:00:00</Finish>
      <Duration>PT2608H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>51</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>133</UID>
      <ID>133</ID>
      <Name>DataConnect Académicos Parte 1 (7)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2025-09-22T08:00:00</Start>
      <Finish>2026-07-06T17:00:00</Finish>
      <Duration>PT2296H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>56</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>134</UID>
      <ID>134</ID>
      <Name>DataConnect Académicos Parte 2 (6)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-08T08:00:00</Start>
      <Finish>2026-08-14T17:00:00</Finish>
      <Duration>PT536H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>135</UID>
      <ID>135</ID>
      <Name>Pruebas Integrales</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2027-07-02T17:00:00</Finish>
      <Duration>PT3784H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>5</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>136</UID>
      <ID>136</ID>
      <Name>Preparación de pruebas GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2026-07-24T17:00:00</Finish>
      <Duration>PT1040H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>28</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>137</UID>
      <ID>137</ID>
      <Name>GL2 · Preparación de casos</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-30T08:00:00</Start>
      <Finish>2026-07-03T17:00:00</Finish>
      <Duration>PT760H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>32</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>138</UID>
      <ID>138</ID>
      <Name>GL2 · Preparación técnica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-07-24T17:00:00</Finish>
      <Duration>PT424H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>139</UID>
      <ID>139</ID>
      <Name>GL2 · Configuración sistemas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-06T08:00:00</Start>
      <Finish>2026-07-24T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>140</UID>
      <ID>140</ID>
      <Name>GL2 · Preparación de ejecución</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-13T08:00:00</Start>
      <Finish>2026-07-17T17:00:00</Finish>
      <Duration>PT760H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>44</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>141</UID>
      <ID>141</ID>
      <Name>Ciclo 1 GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-07-27T08:00:00</Start>
      <Finish>2026-10-19T17:00:00</Finish>
      <Duration>PT672H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>142</UID>
      <ID>142</ID>
      <Name>Ciclo 2 GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-10-20T08:00:00</Start>
      <Finish>2026-12-29T17:00:00</Finish>
      <Duration>PT560H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>143</UID>
      <ID>143</ID>
      <Name>Preparación pruebas GL3</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-03-05T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>144</UID>
      <ID>144</ID>
      <Name>GL3 · Preparación casos (Financiero)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-03-05T08:00:00</Start>
      <Finish>2027-04-02T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>145</UID>
      <ID>145</ID>
      <Name>Ciclo 1 GL3</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-04-19T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT336H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>146</UID>
      <ID>146</ID>
      <Name>Ciclo 2 GL3</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-06-01T08:00:00</Start>
      <Finish>2027-07-02T17:00:00</Finish>
      <Duration>PT248H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>147</UID>
      <ID>147</ID>
      <Name>Despliegue / Cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT2496H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>148</UID>
      <ID>148</ID>
      <Name>Definición Cutover GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT704H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>149</UID>
      <ID>149</ID>
      <Name>GL2 · Definición Cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-08-28T17:00:00</Finish>
      <Duration>PT704H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>150</UID>
      <ID>150</ID>
      <Name>GL2 · Preparación Cutover (cierre + ramos)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-12-14T08:00:00</Start>
      <Finish>2027-02-16T17:00:00</Finish>
      <Duration>PT512H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>151</UID>
      <ID>151</ID>
      <Name>GL2 · Preparación carga final</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-01-14T08:00:00</Start>
      <Finish>2027-02-11T17:00:00</Finish>
      <Duration>PT224H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>152</UID>
      <ID>152</ID>
      <Name>GL2 · Cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-02-01T08:00:00</Start>
      <Finish>2027-02-22T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>153</UID>
      <ID>153</ID>
      <Name>GL2 · GoLive</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-02-23T08:00:00</Start>
      <Finish>2027-03-15T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>154</UID>
      <ID>154</ID>
      <Name>GL2 · Soporte</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-03-16T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT192H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>155</UID>
      <ID>155</ID>
      <Name>GL3 · Clonación ambientes PROD→TEST</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-03-03T08:00:00</Start>
      <Finish>2027-03-12T17:00:00</Finish>
      <Duration>PT72H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>156</UID>
      <ID>156</ID>
      <Name>GL3 · Cutover</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-08-03T08:00:00</Start>
      <Finish>2027-08-13T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>157</UID>
      <ID>157</ID>
      <Name>GL3 · GoLive Financiero</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-08-16T08:00:00</Start>
      <Finish>2027-08-20T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>158</UID>
      <ID>158</ID>
      <Name>Cutover GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-02-01T08:00:00</Start>
      <Finish>2027-02-22T17:00:00</Finish>
      <Duration>PT168H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>159</UID>
      <ID>159</ID>
      <Name>GoLive GL2 + Soporte</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-02-23T08:00:00</Start>
      <Finish>2027-04-09T17:00:00</Finish>
      <Duration>PT360H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>160</UID>
      <ID>160</ID>
      <Name>Gestión del Cambio</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2025-01-07T08:00:00</Start>
      <Finish>2027-05-28T17:00:00</Finish>
      <Duration>PT6968H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>41</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>161</UID>
      <ID>161</ID>
      <Name>Comunicación · Adopción</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2025-01-07T08:00:00</Start>
      <Finish>2027-05-28T17:00:00</Finish>
      <Duration>PT6968H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>41</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>162</UID>
      <ID>162</ID>
      <Name>Modelo Operativo</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2027-04-30T17:00:00</Finish>
      <Duration>PT3280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>3</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>163</UID>
      <ID>163</ID>
      <Name>Diseño MO Académico</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2026-08-19T17:00:00</Finish>
      <Duration>PT1248H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>9</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>164</UID>
      <ID>164</ID>
      <Name>Gestionar oferta académica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-16T08:00:00</Start>
      <Finish>2026-08-10T17:00:00</Finish>
      <Duration>PT1176H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>29</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>165</UID>
      <ID>165</ID>
      <Name>Gestionar planificación académica</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-02T08:00:00</Start>
      <Finish>2026-07-09T17:00:00</Finish>
      <Duration>PT784H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>11</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>166</UID>
      <ID>166</ID>
      <Name>Gestionar admisión de estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-03-23T08:00:00</Start>
      <Finish>2026-08-18T17:00:00</Finish>
      <Duration>PT1184H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>15</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>167</UID>
      <ID>167</ID>
      <Name>Ejecutar docencia</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-06T08:00:00</Start>
      <Finish>2026-06-10T17:00:00</Finish>
      <Duration>PT520H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>43</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>168</UID>
      <ID>168</ID>
      <Name>Gestionar registro académico</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-04-14T08:00:00</Start>
      <Finish>2026-07-23T17:00:00</Finish>
      <Duration>PT800H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>1</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>169</UID>
      <ID>169</ID>
      <Name>Gestionar los profesores</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-07-13T17:00:00</Finish>
      <Duration>PT336H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>170</UID>
      <ID>170</ID>
      <Name>Gestionar inscripción de asignaturas</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-15T08:00:00</Start>
      <Finish>2026-08-04T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>171</UID>
      <ID>171</ID>
      <Name>Gestionar graduación de estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-06-29T08:00:00</Start>
      <Finish>2026-08-07T17:00:00</Finish>
      <Duration>PT312H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>172</UID>
      <ID>172</ID>
      <Name>Gestionar servicios a estudiantes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-20T08:00:00</Start>
      <Finish>2026-08-18T17:00:00</Finish>
      <Duration>PT232H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>173</UID>
      <ID>173</ID>
      <Name>Configuraciones backoffice</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-07-13T08:00:00</Start>
      <Finish>2026-08-19T17:00:00</Finish>
      <Duration>PT296H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>174</UID>
      <ID>174</ID>
      <Name>Presentación diseño MO (Postgrado)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-19T08:00:00</Start>
      <Finish>2026-09-03T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>175</UID>
      <ID>175</ID>
      <Name>Preparación puesta en marcha (Postgrado)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-08-20T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT1240H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>176</UID>
      <ID>176</ID>
      <Name>Preparación puesta en marcha (Pregrado)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2026-09-22T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT976H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>177</UID>
      <ID>177</ID>
      <Name>Monitoreo y estabilización MO</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>3</OutlineLevel>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-04-30T17:00:00</Finish>
      <Duration>PT480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>178</UID>
      <ID>178</ID>
      <Name>Preparación puesta en marcha MO</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2026-08-20T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT1240H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>179</UID>
      <ID>179</ID>
      <Name>Monitoreo / Estabilización MO</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>2</OutlineLevel>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-04-30T17:00:00</Finish>
      <Duration>PT480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>180</UID>
      <ID>180</ID>
      <Name>◆ Inicio Definición Cutover GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-06-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>181</UID>
      <ID>181</ID>
      <Name>◆ Inicio Ciclo 1 Pruebas Integrales GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-07-27T08:00:00</Start>
      <Finish>2026-07-27T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>182</UID>
      <ID>182</ID>
      <Name>◆ Cierre Ciclo 1 Pruebas Integrales GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-10-19T08:00:00</Start>
      <Finish>2026-10-19T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>183</UID>
      <ID>183</ID>
      <Name>◆ Inicio Ciclo 2 Pruebas Integrales GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-10-20T08:00:00</Start>
      <Finish>2026-10-20T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>184</UID>
      <ID>184</ID>
      <Name>◆ Cierre Ciclo 2 Pruebas Integrales GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2026-12-29T08:00:00</Start>
      <Finish>2026-12-29T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>185</UID>
      <ID>185</ID>
      <Name>◆ Fin Preparación Cutover GL2</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-02-11T08:00:00</Start>
      <Finish>2027-02-11T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>186</UID>
      <ID>186</ID>
      <Name>◆ Cutover GL2 (ejecución)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-02-22T08:00:00</Start>
      <Finish>2027-02-22T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>187</UID>
      <ID>187</ID>
      <Name>◆ Go Live 2 — BigBang Pregrado+Postgrado</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-03-01T08:00:00</Start>
      <Finish>2027-03-01T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>188</UID>
      <ID>188</ID>
      <Name>◆ Go Live 3 — Toma de Ramos Masiva</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-07-19T08:00:00</Start>
      <Finish>2027-07-19T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>189</UID>
      <ID>189</ID>
      <Name>◆ Cutover Go Live 3 Financiero</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-08-13T08:00:00</Start>
      <Finish>2027-08-13T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
    <Task>
      <UID>190</UID>
      <ID>190</ID>
      <Name>◆ Go Live 3 Financiero</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <OutlineLevel>1</OutlineLevel>
      <Start>2027-08-16T08:00:00</Start>
      <Finish>2027-08-16T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <PercentComplete>0</PercentComplete>
      <Milestone>1</Milestone>
    </Task>
  </Tasks>
</Project>